Case Study – Approval timelines on track for applications

Approval timelines on track for applications graph

A total of 7584 mining and petroleum exploration applications were received in 2016-17 compared with 6720 in 2015-16.

There was a surge in exploration applications submitted to DMP during 2016-17 reflecting increased interest in gold exploration in the State.

There was a 30 per cent increase in the number of Programme of Work (PoW) applications during 2016-17 with 2232 received compared to 1732 in 2015-16.

The number of PoW applications increased in the second half of the financial year:

  • September 2016 Quarter – 502
  • December 2016 Quarter – 421
  • March 2017 Quarter – 640
  • June 2017 Quarter – 669

Ninety seven per cent of the 2232 PoW applications were finalised within thirty business days.

PoW applications must be approved prior to any ground disturbing activities with mechanised equipment being undertaken.

The department’s performance objective is to finalise more than 80 per cent of all applications within target timelines. Target  timelines vary according to the type of application. For more details visit www.dmp.wa.gov.au/Investors/Approvals